Reporting · markets
PowerCompute orders 600 Antminer S21++ miners for mid-December deployment
PowerCompute is buying 600 miners for about $1 million in cash and expects them running by mid-December, while its latest release flags going-concern doubt.


Quick take
- PowerCompute has ordered 600 Antminer S21++ miners for about $1 million paid in cash.
- Its third-quarter mined bitcoin rose 35.8% to 23.9 BTC while revenue fell to about $1.9 million.
- The company expects the new hardware to add roughly 10% more active hashrate once it is delivered and installed.
NewsBTC reported that PowerCompute has ordered 600 Antminer S21++ mining machines and will pay about $1 million in cash for them. Management expects the units to be deployed by mid-December, and the company aims to raise active hashrate by roughly 10%. The deployment timing is also a management expectation. A replacement at its Mississippi facility is also expected to add 80 to 85 PH/s.
Third-quarter results show the company mined 23.9 BTC, up 35.8%. Revenue fell to about $1.9 million from $2.2 million, while the mining margin rose to 50.7% from 29% in the prior quarter. The company posted an operating loss of about $0.9 million but reported net income near $0.4 million.
The latest release also disclosed going-concern doubt. Management's estimate of the added capacity depends on the machines being delivered and installed on schedule. Until those machines are running, the added capacity remains a management estimate rather than a measured result.
Sources
Machine-written from the publishers’ reports and checked against them · How Dextape writes
Mentioned in this story
CoinGecko last prints. Not a Dextape quote.